Project Management Glossary Terms
Terms
undefined, object
copy deck
- AC
- Actual Cost
- ACWP
- Actual cost of work preformed
- AD
- Activity description
- ADM
- Arrow Diagramming Method
- AF
- Actual Finish date
- AOA
- Activity on Arrow
- AON
- Activity on Node
- AS
- Actual Start Date
- BAC
- Budget at Completion
- BCWP
- Budgeted Cost of Work Performed
- BCWS
- Budgeted Cost of Work Scheduled
- CAP
- Cost Account Plan
- CCB
- Change Control Board
- CPFF
- Cost Plus Fixed Fee
- CPI
- Cost Performance Index
- CPIF
- Cost Plus Incentive Fee
- CPM
- Critical Path Method
- CV
- Cost Variance
- DD
- Data Date
- EAC
- Estimate at Completion
- EF
- Early Finish date
- ES
- Early Start Date
- ETC
- Estimate (or Estimated) To Complete (or completion)
- EV
- Earned Value
- EVM
- Earned Value Management
- FF
- Free Float or Finish-Finish
- FFP
- Firm Fixed Price
- FPIF
- Fixed Price Incentive Fee
- GERT
- Graphical Evaluation and Review Technique
- IFB
- Invitation for Bid
- LF
- Late Finish Date
- LOE
- Level of Effort
- LS
- Late Start date
- MPM
- Modern Project Management
- OBS
- Organization (al) Breakdown Structure
- PC
- Percent Complete
- PDM
- Precedence Diagramming Method
- PERT
- Chart.
- PF
- Planned Finnish Date
- PM
- Project Manager or Project Management
- PMBOK
- Project Management Book of Knowledge
- PMP
- Project Management Professional
- PS
- Planned Start Date
- QA
- Quality Assurance
- QC
- Quality Control
- RAM
- Responsibility Assignment Matrix
- RDU
- Remaining Duration
- RFP
- Request For Proposal
- RFQ
- Request For Quote
- SF
- Scheduled Finish Date
- SOW Statement
- Of
- SPI Schedule
- Performance
- SS Scheduled
- Start
- SV Schedule
- Variance.
- TC Target
- Completion.
- TF Target
- Float
- TS Target
- Start
- TQM Total
- Quality
- VE
- WBS Work
- Breakdown
- Accountability
- Matrix.
- Activity.
- Activity
- on
- Actual
- Start
- Administrative
- Closure.
- Application
- Area.
- Arrow.
- Arrow
- Diagramming
- As-of
- Date.
- Assumptions.
- Assumption
- Analysis. A
- Backward
- pass.
- Bar
- Chart.
- Baseline.
- Baseline
- Start
- Brainstorming. A
- general
- Budget
- Estimate.
- Budgeted
- Cost
- Buffer. See
- reserve
- Calendar
- unit.
- Change
- in
- Chart
- of
- Charter.
- Checklist. A
- listing
- Component.
- Constraint.
- Applicable
- Code
- of
- Communications
- Planning.
- Concurrent
- Engineering.
- Contingencies.
- Contingency
- Reserve.
- Contract.
- Fixed
- Price
- Cost
- Variance.
- Unit
- price
- Time
- &
- Contract
- Closeout.
- Control.
- Control
- Charts.
- Corrective
- Action.
- Crashing.
- Critical
- Path
- Current
- Start
- Data
- Date.
- Definitive
- estimate.
- Decision
- Tree
- Deliverable.
- Dependency.
- Dummy
- Activity.
- Duration
- Compression.
- Early
- Start
- Earned
- Value
- Effort.
- Element. One
- of
- Estimate.
- Estimate
- To
- Event
- on
- Exception
- Report.
- Expected
- Monetary
- Fast
- Tracking.
- Finish
- Date.
- Finish-to-Finish.
- Finish-to-Start.
- Firm
- Fixed
- Float.
- Forecast
- Final
- Forward
- Pass.
- Fragnet.
- Free
- Float.
- Functional
- Organization. An
- Gnatt
- Chart.
- Grade.
- Graphical
- Evaluation
- Hammock.
- Hanger.
- Information
- Distribution.
- Initiation.
- Integrated
- cost/Schedule
- Invitation
- for
- Key
- Event
- Lag.
- Late
- Start
- Lead.
- Lessons
- Learned. The
- Level
- of
- Leveling.
- Life
- cycle
- Line
- Manager.
- Link.
- Logic.
- Logic
- Diagram.
- Logical
- relationship.
- Finish-to-start-
- the
- Finish-to-Finish-
- the
- Start-to-start-
- the
- Start-to-finish-the
- “fromâ€
- Loop.
- Management
- Reserve.
- Master
- Schedule.
- Mathematical
- Analysis.
- Matrix
- Organization.
- Milestone.
- Milestone
- schedule.
- Mitigation.
- Modern
- Project
- Monitoring.
- Monte
- Carlo
- Near-critical
- Activity.
- Network.
- Network
- Path. Any
- Node.
- Order
- of
- Organizational
- Planning.
- Overall
- change
- Overlap.
- Parametric
- Estimating.
- Pareto
- diagram.
- Path.
- Path
- float.
- Percent
- complete.
- Performance
- Reporting.
- Performing
- Organization.
- Phase.
- Planned
- Start
- Precedence
- Relationship.
- Predecessor
- Activity.
- Probability
- Impact
- Procurement
- Planning.
- Product
- Scope. The
- Program.
- Program
- Evaluation
- Project.
- Project
- Manager